Transmission Tower Construction & Cable Installation

The tower installation is one of precedent activities for transmission power cable. It is permitted to install the tower when completing the backfill and inspecting witness by TPC.
There are 2 methods of installing tower, namely “Leg Gin Pole Method” and “Moveable Crane Method”. “Leg Gin Pole Method” is suitable for adopting in the mountain area or the truck or crane can not be accessed. “Moveable Crane Method” is suitable for adopting in the flat terrain area or easy-access.
 
"Jugong ~ Jiamin connection to Yunlin 161KV overhead transmission line turnkey project (TPC)" is the first turnkey project of tower in 2006. We are familiar with the TPC procedure of tower planning design, material inspection under TPC Class A inspection, foundation construction, tower installation, overhead transmission cable laying.